FRANK RAINIERI MARRANZINI: CREATOR OF DREAMS

Housing Development Timeline

First stage (including 41 residences for partners and the orphanage)

1999

First stage of PCIS and school opening (PK-7)

2000

Second stage (two apartment blocks with

16 units total, 4 villas. First stage of Galerías)

2002

Construction of private villas begins.

2003

By year’s end, 20 houses (including four executive housing units developed

by GPC) and two apartment blocks had been built. The church is finished

and opened to the public. Total: 24 homes, 40 apartments.

Second stage of Galerías is finalized.

2004

By year’s end, 35 houses and three apartment blocks had been built.

Total: 59 homes, 70 apartments.

36 additional private villas and two more apartment

blocks are built. Total: 95 homes, 86 apartments.

2005

Third stage of Village is finalized. Second stage of

PCIS is finalized. An additional 65 private villas and

two more apartment blocks are built. Total: 160 homes,

110 apartments.

2006

Third stage of Galerías is finalized. Third stage of PCIS is finalized.

2007

First office building is built on the boulevard. A total of

75 additional villas and four more apartment blocks are built.

Total: 235 homes, 190 apartments, and one commercial building.

Fourth and fifth stages finalized. A total of 98 additional private

villas, three more apartment blocks, and an apartment cluster are built.

Second commercial building is built.

Total: 333 homes, 437 apartments, 2 commercial buildings.

2008

An additional 11 villas are built, with 74 under construction. A total

of 111 apartments under construction. Three new commercial

buildings under construction. Projected year-end total: 418 homes,

548 apartments, and 5 commercial buildings.

2009

(to date)

Hacienda

Construction begins

2007

La Cana driving range renovations

2009